青砖墙面施工
. 青砖墙面施工 一、施工条件 1.主体承重结构已施工完毕; 2.多孔砖衬里墙 (沿高度方向每 500mm留设一道钢筋网片,与古建停泥墙拉 结 )施工完毕; 3.古建停泥砖墙的测量放线工作必须经过验收; 4.施工机具已准备到位; (1) 主要工具:瓦刀、大铁锹、手推车、无齿锯、打磨机等; (2) 检测工具:水准仪、钢卷尺、铝合金靠尺、水平尺、线坠等; 5.材料已经进场,砖料加工已进行一个阶段。 二、施工准备 1.根据主体结构上弹的建筑 +500线控制最下面一皮砖,根据最下面一皮砖 的标高对砌筑高度进行控制。 2.为了提高小气块墙体的施工效率, 保证施工砌筑质量, 砌筑前根据墙体分 段尺寸,绘制墙体的青砖排列施工图,其主要内容: (1) 墙体的尺寸要尽量符合青砖的模数。按照应三顺一丁砌法,上下皮错缝 搭砌,每两皮为一循环。 (2) 对于体长度不满足停泥砖模数的墙体排砖后用七分头进行调整,端
装修砌墙工艺标准、过程汇总(红砖墙、青砖墙)
1 / 21 目 录 视频学习: ··························································· 1 红砖质量鉴别: ····················································· 1 墙砖基础知识 :························································· 1 价格计算 ····························································· 2 注意事项 ····························································· 3 墙体泛霜的问题 ··································