Foreword
1 Scope
2 Normative References
3 General Provisions
4 Inspection before Start-up Test
5 Water Filling Test
6 Start-up and No-load Test
7 Test of Generator with Main Transformer and HV Switchgear
8 Synchronization and Loading Test
9 72h Continuous Test Run with Load
10 Handover and Putting into Commercial Operation
Appendix A (Informative) Recording Form for Load Shedding Test
Appendix B (Informative) List of Documents to be Handed over for Acceptance of Unit Start-up
Test Run
References2100433B