房建施工方案英文版
Page 1 of 10 The Main Construction Working Methods Chapter one Section 1 surveying, setting out, axis and elevation control 0. Site management The personnel to carry out this project consists of contract manager, Quantity Surveyor, Site Engineer, General foreman, trades foremen and other professionals. The General foreman shall always stay on site to reconcile the distributions of project
仪表施工方案英文版
Instrument construction method 1.General The project covers dismantling of lod skid and isntallation of new skid of PRAXAIR(Yueyang).Including:16 temperature transmitters,20 transmitters,19 solennoid valves,12 electrical heater,3 istrument panels,1 junction box and piping,cable laying,wiring and calibration. 2.Codes and standards Industrial Automation Insstrument Construction & Acceptance C